Illinois Blitz Build |
|||
Prep
day 1, Footings in the ground. |
||||
Prep
day
2, Foundation forms and basement walls are poured. |
||||
|
|
||||
Prep
day
4, Decking going on. |
||||
Prep
day 5, Deck is on, and we're ready for the volunteers. |
||||
![]() ![]() |
Day 1, Our first full volunteer day, family in attendance and the walls start to go up. |
|||
![]() ![]() |
Day 2, second floor starts to take shape and we get a plumbing special delivery. | |||
![]() ![]() |
Day 3, You can start to see the roof line. We are sheeting and installing siding. | |||
![]() ![]() |
Day 4, Exterior has siding and roof, the interior has electric and plumbing. | |||
![]() ![]() |
Day 5, Pictures of our new homeowner working | |||
![]() ![]() |
Day 6, Rough electrical, plumbing and HVAC as well as siding installation. | |||
![]() ![]() |
Day 7, Insulation first thing in the morning and hanging drywall the rest of the day. | |||
![]() ![]() |
Day 8, Drywall taping completed, exterior doors hung, siding continues. | |||
![]() ![]() |
Day 9, Temperature in the 90's, yet the family is putting in their sweat equity hours with a smile. | |||
![]() ![]() |
Day 10, Priming and painting crews inside, siding outside | |||
![]() ![]() |
Day 11, Cabinet and flooring installation begins. | |||
![]() ![]() |
Day 12, Some rooms look ready, some finishing yet to be complete.. | |||
![]() ![]() |
Day 13, Ready for the big day. | |||
![]() ![]() |
House Blessing, A job well done, a time to rejoice, and a family ready for a new beginning. | |||